Cost estimate for major Pool and Jacuzzi expenses August 10, 1979
Note: Pool excavation costs are for earlier site where there
were some access problems. Cost in new location may be less.
Total cost has increased because of the fence and because
prices are going up.
Initial site preparation (moving several small trees and shrubs) $ 500
Geological site survey 600
Pool 22' x 36' 712 sq. ft. (complete with plastering and finishing) 11545
Spa with separate equipment, 175,000 Btu heater 2600
Pool auxillary heater, 300,000 Btu 650
Commercial pack (circulating pump, plumbing, chlorinator, etc.) 2200
Pool sweep (not absolutely necessary if pool cover is installed) 560
Underwater lights (2) (not absolutely necessary) 220
Extending roof of existing toilet building and adding dressing rooms 1500
Solar heating panels with mounts (14 panels and run) 7800
Decks (concrete, rock salt finish, wire mesh reinforcing with footings) 3100
Electrical power hook-up 200
Gas line (could use propane if cost exceeds this amount) 1000
Key operated automatic pool cover 3500
Fencing (180 lineal feet, chain link with key operated gate) 1400
Landscaping (minimum only, may want to do more) 1000
Estimated total cost $38375
10% Contingency 3838
Cost with contingency $42213
(Estimate prepared by Arthur Samuel, on the basis
of quotes received from a variety of sources. In
many cases only a single quote has been received
and costs might be less from another supplier.)