Cost estimate for major Pool and Jacuzzi expenses	     August 10, 1979

	Note: Pool excavation costs are for earlier site where there
	were some access problems. Cost in new location may be less.
	Total cost has increased because of the fence and because
	prices are going up.

Initial site preparation (moving several small trees and shrubs)	$  500
Geological site survey							   600
Pool 22' x 36' 712 sq. ft. (complete with plastering and finishing)	 11545
Spa with separate equipment, 175,000 Btu heater				  2600
Pool auxillary heater, 300,000 Btu					   650
Commercial pack (circulating pump, plumbing, chlorinator, etc.)		  2200
Pool sweep (not absolutely necessary if pool cover is installed)	   560
Underwater lights (2) (not absolutely necessary)			   220
Extending roof of existing toilet building and adding dressing rooms	  1500
Solar heating panels with mounts (14 panels and run)			  7800
Decks (concrete, rock salt finish, wire mesh reinforcing with footings)	  3100
Electrical power hook-up						   200
Gas line (could use propane if cost exceeds this amount)		  1000
Key operated automatic pool cover		 			  3500
Fencing (180 lineal feet, chain link with key operated gate)		  1400
Landscaping (minimum only, may want to do more)				  1000

				Estimated total cost			$38375
10% Contingency								  3838

				Cost with contingency 			$42213


(Estimate prepared by Arthur Samuel, on the basis
of quotes received from a variety of sources. In
many cases only a single quote has been received
and costs might be less from another supplier.)